(Summary description)The construction procedures of the aluminum-magnesium-manganese roofing system should be arranged to be continuously completed in an independent construction section. In the construction of the roofing project, if there is a project construction that is higher than the roof in the adjacent area, the construction should be started after the wet work of the adjacent project is completed to protect the roofing project from being damaged or being used as a supporting surface for scaffolding. The aluminum-magnesium-manganese roofing system shall be started after all the processes of its supporting members are completed.
Aluminum-magnesium-manganese roofing panels, aluminum-magnesium-manganese board manufacturers, precautions for aluminum-magnesium-manganese roof construction
(Summary description)The construction procedures of the aluminum-magnesium-manganese roofing system should be arranged to be continuously completed in an independent construction section. In the construction of the roofing project, if there is a project construction that is higher than the roof in the adjacent area, the construction should be started after the wet work of the adjacent project is completed to protect the roofing project from being damaged or being used as a supporting surface for scaffolding. The aluminum-magnesium-manganese roofing system shall be started after all the processes of its supporting members are completed.
- Categories:Company Dynamics
- Author:
- Origin:
- Time of issue:2018-09-04 14:28
- Views:
Precautions for aluminum-magnesium-manganese roof construction
The construction procedures of the aluminum-magnesium-manganese roofing system should be arranged to be continuously completed in an independent construction section. In the construction of the roofing project, if there is a project construction that is higher than the roof in the adjacent area, the construction should be started after the wet work of the adjacent project is completed to protect the roofing project from being damaged or being used as a supporting surface for scaffolding. The aluminum-magnesium-manganese roofing system shall be started after all the processes of its supporting members are completed.
Construction process: roof laying and positioning→purlin support plate installation→purlin installation→aluminum alloy T-shaped fixed seat installation→lightning protection installation→200mm thick glass wool insulation installation→aluminum-magnesium-manganese alloy house Panel & rarr; flooding and roof slab edge construction & rarr; gutter cornice & rarr; roof skylight and other treatment & rarr; handover acceptance.
Installation precautions
Purlin pallet installation:
The purlin pallet is the basis for the connection of the grid ball node and the roof system, and is the main component for adjusting the installation error of the grid. The height of the purlin pallet should be determined according to the measurement data obtained when the roof is placed on site. Only in this way can the roof purlin have enough adjustment space. The purlin support plate and the ball joint bracket are connected by welding, and the welding point must be polished during welding, and the protective coating of the grid is protected from damage during the welding process.
Installation of purlin (c-shaped steel, z-shaped steel):
The purlins (c-shaped steel, z-shaped steel) are arranged horizontally or vertically according to the roof. The purlin and the purlin are connected by welding. Before welding, check whether the top surface of the purlin being installed is flush with the top surface of the adjacent purlin, such as The unevenness should be adjusted, and the top surface height difference of adjacent purlins (c-shaped steel, z-shaped steel) should be within 3~5mm. The cross section and placement direction of the purlin (c-shaped steel, z-shaped steel) at the gutter should be distinguished to prevent installation errors. After installing the purlins for each node, install the tie rods and purlin supports in time to form a stable purlin structure system.
Scan the QR code to read on your phone
More News
-
Aluminum-magnesium-manganese roofing panels, aluminum-magnesium-manganese board manufacturers, precautions for aluminum-magnesium-manganese roof construction
The construction procedures of the aluminum-magnesium-manganese roofing system should be arranged to be continuously completed in an independent construction section. In the construction of the roofing project, if there is a project construction that is higher than the roof in the adjacent area, the construction should be started after the wet work of the adjacent project is completed to protect the roofing project from being damaged or being used as a supporting surface for scaffolding. The aluminum-magnesium-manganese roofing system shall be started after all the processes of its supporting members are completed. - Titanium-zinc plate, aluminum-magnesium-manganese plate, aluminum-magnesium-manganese roof panel installation node processing method 09-04
- Application of aluminum-magnesium-manganese roof panels and aluminum-magnesium-manganese roof panels 09-04